Broadview data-center deal covers five miles of roads—not power or water approval

As of 2026-10-29 · Publication details

First-phase agreement reported October 27, 2026 · miles of reported haul route

Heiken Road segment1 miles of reported haul route [2]
Buffalo Trail Road segment4 miles of reported haul route [2]

Five miles in Yellowstone County, per MTFP. Road lengths are comparable; they are not costs, power use or the area of an approved data center.

Read the values and scale as a table
Common zero; maximum magnitude 4 miles of reported haul route. First-phase agreement reported October 27, 2026.
MeasureValue (miles of reported haul route)Evidence
Heiken Road segment1[2]
Buffalo Trail Road segment4[2]
One mile of Heiken Road plus four miles of Buffalo Trail Road. This limited road agreement does not supply land-use, water or electricity approval.

Yellowstone County, Montana: October 27 MTFP original reporting of a 3–0 first-phase road agreement with Big Sky Digital Infrastructure. Executed contract not captured; approval and terms remain attributed to MTFP.

Yellowstone County’s new agreement is meant to make the developer cover road wear from early work near Broadview, MTFP reports. Its five-mile haul route is concrete; approval of power, water and land use is outside this agreement. [1] [2] [4]

Still open: Executed agreement and October 27 vote/minutes were not captured; approval and terms are attributed to MTFP. All open questions ↓

Read the original report and its linked road-agreement document →
Read the full story

The reporting question: What does Yellowstone County’s new road agreement cover, and who is supposed to pay?

The action is about public roads

Phoebe Tollefson’s October 27 MTFP report says commissioners approved the agreement 3–0. It names Big Sky Digital Infrastructure as the developer and describes a first phase involving roads and a well site. This is a local infrastructure obligation, not evidence that an AI facility is operating. [1] [4]

Who is supposed to carry the cost?

MTFP reports a developer-funded road improvement, inventories and weekly inspections, a county-approved maintenance contractor and a $250,000 surety bond. The chart compares the two segments of the five-mile haul route. Neither the mileage nor the bond establishes the project’s total cost or proves taxpayers can face no other exposure. [3] [2]

The next decisions are separate

Plecker expressly separated road use from land-use, water and electricity approval. The company’s November 1 work expectation and May 2027 well target remain plans. The executed contract and fresh vote record were not captured here; use the original report to inspect the reported obligations and its document link, keeping the older unsigned draft distinct from a signed agreement. [4] [5]

Archive photograph · 2014-10-05 · Broadview, Montana

An older commercial building and street in Broadview, Montana.
Archive: Broadview, Montana, October 5, 2014.Town context only; not the proposed facility, its haul route or a current construction photograph.Photo: Eric Friedebach / Wikimedia Commons · Original source ↗ · CC BY 3.0 ↗Original file unchanged; displayed at responsive sizes.
How we know5 scoped claims · 1 source recordView evidence

Each claim keeps its full assertion, date, source passage and limits. Source counts describe records, not independent corroboration.

1.A limited agreementAttributed

MTFP reports that Yellowstone County commissioners voted 3–0 on October 27 to finalize a first-phase road agreement with Big Sky Digital Infrastructure.

Scope
Yellowstone County, Montana: October 27 MTFP original reporting of a 3–0 first-phase road agreement with Big Sky Digital Infrastructure. Executed contract not captured; approval and terms remain attributed to MTFP.
Evidence passage
Opening paragraphs: commission vote and first-phase road-use agreement.
As of
2026-10-29
Limit
Attributed approval report, not NTDS inspection of the executed contract.
Phoebe Tollefson / Montana Free Press, October 27 ↗

Retrieved 2026-10-29T08:05:04.752Z · Montana Free Press

Approval and contract terms are reported by MTFP; executed agreement and vote record were not independently captured. An accessible older unsigned draft is not treated as final.

2.Five miles, two road segmentsAttributed

The reported haul route includes one mile of Heiken Road and four miles of Buffalo Trail Road to the company’s property.

Scope
Yellowstone County, Montana: October 27 MTFP original reporting of a 3–0 first-phase road agreement with Big Sky Digital Infrastructure. Executed contract not captured; approval and terms remain attributed to MTFP.
Evidence passage
Route paragraph beginning The agreement pertains to the route.
As of
2026-10-29
Limit
Distances are route lengths, not construction costs or project scale.
Phoebe Tollefson / Montana Free Press, October 27 ↗

Retrieved 2026-10-29T08:05:04.752Z · Montana Free Press

Approval and contract terms are reported by MTFP; executed agreement and vote record were not independently captured. An accessible older unsigned draft is not treated as final.

3.Developer obligationsAttributed

MTFP reports developer-paid road work, condition inventories, weekly inspections, a county-approved maintenance contractor and a $250,000 surety bond.

Scope
Yellowstone County, Montana: October 27 MTFP original reporting of a 3–0 first-phase road agreement with Big Sky Digital Infrastructure. Executed contract not captured; approval and terms remain attributed to MTFP.
Evidence passage
Road-condition, weekly-inspection, contractor and surety-bond paragraphs.
As of
2026-10-29
Limit
A bond is not total project cost, a payment already made, or a proven limit on all public exposure.
Phoebe Tollefson / Montana Free Press, October 27 ↗

Retrieved 2026-10-29T08:05:04.752Z · Montana Free Press

Approval and contract terms are reported by MTFP; executed agreement and vote record were not independently captured. An accessible older unsigned draft is not treated as final.

4.What the deal does not grantAttributed

Public Works Director Monica Plecker said the agreement concerned road condition and use, not approval for land use, water or electricity, MTFP reports.

Scope
Yellowstone County, Montana: October 27 MTFP original reporting of a 3–0 first-phase road agreement with Big Sky Digital Infrastructure. Executed contract not captured; approval and terms remain attributed to MTFP.
Evidence passage
Plecker comments on scope; later paragraphs on initial phase and future agreement.
As of
2026-10-29
Limit
Does not establish the status of every separate permit or prove an operating facility.
Phoebe Tollefson / Montana Free Press, October 27 ↗

Retrieved 2026-10-29T08:05:04.752Z · Montana Free Press

Approval and contract terms are reported by MTFP; executed agreement and vote record were not independently captured. An accessible older unsigned draft is not treated as final.

5.Construction dates remain plansAttributed

The report describes a company expectation to start November 1 and a planned well-drilling date of May 1, 2027.

Scope
Yellowstone County, Montana: October 27 MTFP original reporting of a 3–0 first-phase road agreement with Big Sky Digital Infrastructure. Executed contract not captured; approval and terms remain attributed to MTFP.
Evidence passage
Final paragraphs describing company plans and initial-phase work.
As of
2026-10-29
Limit
Neither date is an observed start or completion; future phases may need another agreement.
Phoebe Tollefson / Montana Free Press, October 27 ↗

Retrieved 2026-10-29T08:05:04.752Z · Montana Free Press

Approval and contract terms are reported by MTFP; executed agreement and vote record were not independently captured. An accessible older unsigned draft is not treated as final.

What remains open.

  • Executed agreement and October 27 vote/minutes were not captured; approval and terms are attributed to MTFP.
  • The county-hosted October draft has blank signature fields and is outside installed capture policy; it cannot authenticate execution.
  • No verified electricity agreement, water right, paid customer, project financing or delivery outcome is established.
  • The bond is not adopted as total spending or a ceiling on all county exposure.

Reopen this account if the named original record is corrected or if an executed agreement, new permit or verified work record changes the stated scope.

THIS STORY IN TIME

Keep the dates with the story.

Reported development
Evidence as of
First retained publication
This version published

Publication times are Central. A development date and an evidence date can differ. Missing dates remain unrecorded.

Retained versions of this story · 1
  1. Oct 29, 2026, 7:00 AM · Broadview data-center deal covers five miles of roads—not power or water approval · Revision 1
Explore Technology →

What readers add.

Comments are reviewed before they appear. Max includes five comments and two custom story requests each day.

Loading reviewed comments…

Add a comment with Max →