Saint Paul celebrates a rebuilt bridge—with reopening still ahead

MPR reports an October 24 community walk and ribbon-cutting at the rebuilt Kellogg–Third Street bridge. Traffic reopening is planned by November 15; the celebration does not mean the everyday route is open. [1] [3]

Check Saint Paul’s bridge project updates and detours before planning a trip →

Saint Paul, Minnesota: MPR’s October 25 original report on the October 24 Kellogg–Third Street bridge ceremony and planned traffic reopening by November 15. Ceremony, construction progress and actual everyday access are different states.

  • 1 source record
  • Original reporting
  • MPR News

Still open: Actual daily public reopening and final completion are not established. All open questions ↓

Reporting question · As of 2026-10-25

The question: What did Saint Paul celebrate at its rebuilt Kellogg–Third Street bridge, and when can people expect the connection back?

Saint Paul, Minnesota: MPR’s October 25 original report on the October 24 Kellogg–Third Street bridge ceremony and planned traffic reopening by November 15. Ceremony, construction progress and actual everyday access are different states.

October 24: celebrated

Community walk and ribbon-cutting, reported by MPR October 25.

[1]

By November 15: planned

Traffic reopening target; not a confirmed opening today.

[3]

Work still remains

Railings and landscape restoration; check current access before travel.

[3]

Three different project states, not a measured construction timeline. MPR’s October 25 report; reopening and benefits remain prospective.

Read the process as a table
ComponentMeaningEvidence
October 24: celebratedCommunity walk and ribbon-cutting, reported by MPR October 25.[1]
By November 15: plannedTraffic reopening target; not a confirmed opening today.[3]
Work still remainsRailings and landscape restoration; check current access before travel.[3]
Three different project states, not a measured construction timeline. MPR’s October 25 report; reopening and benefits remain prospective.

Archive photograph · 2025-04-09 · Saint Paul Union Depot, Saint Paul, Minnesota, United States

Benches and people inside Saint Paul Union Depot’s vaulted waiting hall.
Archive: Saint Paul Union Depot, April 9, 2025.Nearby transport context only. This interior photograph does not show the rebuilt bridge, October 24 ceremony, current access or any person interviewed for this report.Photo: Michael Barera / Wikimedia Commons · Original source ↗ · CC BY-SA 4.0 ↗Original file unchanged; displayed at responsive sizes.

Understand the story.

A walk toward reconnection

Neighbors had a chance to walk across a connection they have missed. MPR’s Matt Mikus reports from the October 24 ribbon-cutting and quotes East Side residents looking forward to a more direct route downtown. The old bridge closed in July 2024. NTDS did not attend or interview those residents. [1] [2]

Room for more ways to travel

MPR describes four vehicle lanes and barrier-separated space for walking and cycling, with rebuilt intersections near Union Depot and Mounds Boulevard. Those are design features intended to improve the connection. The report does not measure safer journeys, shorter commutes or how many people will use it. [2]

The ribbon is cut; the route is still a plan

The reported target is traffic reopening by November 15. Railing installation and landscape restoration remain. Before a trip, check the city’s project page for construction updates and detours, and follow posted restrictions. Saturday’s community event is not confirmation of unrestricted public access today. [1] [3]

Read the funding number carefully

MPR reports $92.7 million in secured funding, combining state legislative bonds, federal grants and local funds. That figure describes project financing. It is not an independently audited final bill, a household saving or proof that every promised transport benefit has arrived. [4]

How we know4 scoped claims · 1 source recordView evidence

Each claim keeps its full assertion, date, source passage and limits. Source counts describe records, not independent corroboration.

1.A community milestoneAttributed

MPR’s October 25 account reports that people walked across the replacement Kellogg–Third Street bridge during an October 24 ribbon-cutting ceremony. The account quotes East Side residents looking forward to their connection downtown returning.

Scope
Saint Paul, Minnesota: MPR’s October 25 original report on the October 24 Kellogg–Third Street bridge ceremony and planned traffic reopening by November 15. Ceremony, construction progress and actual everyday access are different states.
Evidence passage
Opening paragraphs and both October 24 photograph captions. Resident account beginning Derek and Tracy Sciacca live on the east side.
As of
2026-10-25
Limit
Reported by MPR, whose reporter is credited on the ceremony photographs. NTDS did not attend or conduct the interviews.
MPR News · Matt Mikus · October 25 original report ↗

Retrieved 2026-10-25T14:11:40.337Z · MPR News

One original newsroom account, including reporter-credited ceremony photographs and attributed resident/official statements. Not an NTDS visit, interview, engineering inspection or financial audit.

2.A connection being restoredAttributed

MPR reports that the former bridge connecting downtown Saint Paul with Mounds Boulevard closed July 29, 2024. The replacement design includes four vehicle lanes and separated walking and cycling space.

Scope
Saint Paul, Minnesota: MPR’s October 25 original report on the October 24 Kellogg–Third Street bridge ceremony and planned traffic reopening by November 15. Ceremony, construction progress and actual everyday access are different states.
Evidence passage
Paragraph beginning The new bridge will have four lanes; paragraphs beginning The former half-mile concrete bridge and The bridge replacement stems.
As of
2026-10-25
Limit
Design and intended access do not establish measured safety, accessibility compliance, traffic savings or current public opening.
MPR News · Matt Mikus · October 25 original report ↗

Retrieved 2026-10-25T14:11:40.337Z · MPR News

One original newsroom account, including reporter-credited ceremony photographs and attributed resident/official statements. Not an NTDS visit, interview, engineering inspection or financial audit.

3.Reopening is still aheadAttributed

MPR reports planned traffic reopening by November 15, 2026, while railing installation and landscape restoration remain work to be done.

Scope
Saint Paul, Minnesota: MPR’s October 25 original report on the October 24 Kellogg–Third Street bridge ceremony and planned traffic reopening by November 15. Ceremony, construction progress and actual everyday access are different states.
Evidence passage
Opening planned reopening date; paragraph beginning While the public works department plans to open.
As of
2026-10-25
Limit
A forecast date is not confirmation of opening. A one-day celebration does not establish daily access for vehicles, walkers or cyclists.
MPR News · Matt Mikus · October 25 original report ↗

Retrieved 2026-10-25T14:11:40.337Z · MPR News

One original newsroom account, including reporter-credited ceremony photographs and attributed resident/official statements. Not an NTDS visit, interview, engineering inspection or financial audit.

4.Funding is not a final auditAttributed

MPR reports $92.7 million in secured project funding: $80.5 million in state legislative bonds, $7 million in federal grants and $5.2 million in local funds.

Scope
Saint Paul, Minnesota: MPR’s October 25 original report on the October 24 Kellogg–Third Street bridge ceremony and planned traffic reopening by November 15. Ceremony, construction progress and actual everyday access are different states.
Evidence passage
Final substantive paragraph beginning The total funding secured for the project.
As of
2026-10-25
Limit
These are reported funding sources, not independently audited final spending or measured household savings. The quoted under-budget assertion is not independently verified.
MPR News · Matt Mikus · October 25 original report ↗

Retrieved 2026-10-25T14:11:40.337Z · MPR News

One original newsroom account, including reporter-credited ceremony photographs and attributed resident/official statements. Not an NTDS visit, interview, engineering inspection or financial audit.

What remains open.

  • Actual daily public reopening and final completion are not established.
  • No independent engineering inspection, final expenditure audit, accessibility assessment or measured commute/safety outcome is attached.
  • The municipal project page is a verified practical help destination, read separately. It is outside installed evidence-capture families and supplies no graph claim or freshness proof. All reported factual claims rely on the full permitted MPR original.

A changed opening notice, revised schedule, closure, source correction, engineering finding or audited final cost would reopen this account. Preserve the distinction between celebration and confirmed access.

THIS STORY IN TIME

Keep the dates with the story.

Reported development
Evidence as of
First retained publication
This version published

Publication times are Central. A development date and an evidence date can differ. Missing dates remain unrecorded.